Grangemouth prepares for major industrial shift as dock works begin
Work has officially transitioned from planning to the delivery phase at Grangemouth, as Falkirk Council moves to ready brownfield sites for the Forth Green Freeport. While the broader Freeport initiative carries an ambitious £7.9 billion target for public and private investment over the next decade, current site activity is focused on immediate infrastructure upgrades designed to unlock long-term development.
Site preparation and infrastructure upgrades
Council-led projects are currently underway to resolve long-standing physical barriers that have previously hindered site development. At South Bridge Street, seed capital funding is being deployed to improve access, install essential drainage, and upgrade utilities to make the brownfield land commercially viable. These foundational works are critical, as they transform idle land into “shovel-ready” sites capable of hosting new industrial tenants.
Additional works are being progressed across the area using Freeport seed capital:

| Location | Project Focus | Investment/Status |
|---|---|---|
| Calachem Site | Land preparation | £5.5 million (approx. 20 acres) |
| Wholeflats | Site preparation | £500,000 |
| Port Area | Electricity capacity | £1 million |
Strategic industrial growth and capacity
The £5.5 million project at the Calachem site is the most significant immediate investment, aimed at transforming 20 acres of brownfield space into serviced industrial land. Officials estimate this specific development has the potential to support up to 1,000 high-skilled jobs. Parallel to this, the Wholeflats site is being prepared to support the proposed Grangemouth Sustainable Manufacturing Campus, which is being delivered in conjunction with the Falkirk and Grangemouth Growth Deal. This campus aims to bridge the gap between industrial concepts and commercial-scale manufacturing.
Infrastructure constraints remain a primary concern for the area, particularly regarding power and utility capacity. The £1 million earmarked for the port is specifically designed to increase electricity capacity to meet future demand from new industrial tenants. According to the latest update from Falkirk Council, these investments are essential to ensure the town remains a competitive location for businesses looking to relocate or expand.

Local impact and governance
Paul Kettrick, Falkirk Council’s Head of Investment, Assets and Climate, emphasised that the current phase is about building a foundation for long-term growth. “Grangemouth already has major strengths as Scotland’s largest port, an export hub and a long-established industrial centre,” Kettrick stated. “The work now focuses on improving infrastructure and addressing practical barriers that can hold projects back.”
As the Accountable Body for the Green Freeport, Falkirk Council oversees the governance and public funding associated with these sites. While the Green Freeport offers tax and customs incentives for sectors like manufacturing and low-carbon energy, businesses are expected to demonstrate clear commitments to job creation, skills development, and net-zero targets. The council will review the progress of these initial delivery phases at a meeting on 25 June, where members will set priorities for the coming year. It is important to note that while these preparations enhance the area’s competitiveness, the final decision to invest rests with private businesses, and the timeline for full site occupancy will depend on market demand.
Source: Falkirk Council News
Context & actions About this article
Source check Council Report Verification
This article is based on the official progress report submitted to Falkirk Council regarding the Forth Green Freeport delivery phase.
- Cross-referenced against the June 2026 council committee papers
- Verified site-specific investment figures for Calachem and Wholeflats
- Confirmed project scope with public records on the Falkirk and Grangemouth Growth Deal
- Source
- Falkirk Council News
- Scope
- Grangemouth
- Updated
- 2026-07-21 08:32